Since our last post, all framing has been completed except for the basement stairs and the family room stairs. Parts of these stairs were missed by RH in the last delivery. They have ordered the missing parts and we should be getting them soon.
All windows and doors, except for the basement exit door have been installed as well. The basement door installation is awaiting a pad that goes below the door, which seems to be missing as well. With the completion of roofing and shingles, we see the complete structure of the house now.
Today there were no construction activities. For this shorter week, plumbing, HVAC installation, Guardian wiring, and Electric Work is planned.
Visual Updates
Dont you just want to grab your sleeping bags now? lol --Ericka
ReplyDeleteThat is a big house! Look at all those windows! :-)
ReplyDeleteLooking awesome! Side access from the garage or extended laundry?
ReplyDeleteSide access is from the garage.
DeleteCongratulations on your newly installed windows and roofs, Namma. It’s definitely a relief to finally see your house being completed. Along with having a new house is maintaining it in good condition. With your roof, you could do a regular inspection once a month, or every few weeks, to check for leaks, damaged shingles, or scattered debris. It would really help in preserving the structural integrity of your roof.
ReplyDeleteAdam Waterford