This week it looks very busy. So far they have done footings and putting up the walls. I went in the evening to see if they have completed the work and found that it was still going on. The worker bees had completed completed putting it up and they were working on securing them. Hopefully they will finish it today. Tomorrow they will pour the concrete, on Thursday they waterproof it and on Friday they will complete the plumbing work.
I also found that the lot next to us has also started the construction process and today was their first day. Good thing is that we don't have to listen to all construction related noises after we move in.
Photo Session:
Footings
Putting up the walls
No comments:
Post a Comment