Pages

Wednesday, June 13, 2012

Garage Flooring, HVAC, Inspections, Pre-Drywall meeting, Drywall installation

Last week was a busy one filled with a lot of activities...the garage flooring, electrical work, guradian work, HVAC installation, HVAC inspection and Framing were all done last week..


We also had our pre-dry wall meeting last week..We went over all the options we have chosen with the PM and his assistant to make sure nothing was missed..We notified them of a stud that was broken..

Our sheet rock was delivered mid last week, but the installation did not begin until today as both our insulation inspection and Framing inspection failed last week...The insulation inspection failed due to missing insulation in a portion of the master bath and a small area in the garage...the cause of the Framing inspection failure was stated as "not tying the raftors to each parallel ceiling joists in the roof of master bed room" whatever that means...Both inspections were scheduled again on the 11th...we passed the insulation inspection but framing failed again as the front porch has not been constructed yet..There was a 3-day delay in sheet rock installation due to the inspection failure..I am sure they'll make up for the lost days...

Inspite of the framing inspection failure, sheet rock installation started yesterday...the entire first and second floor were completed yesterday...they should be done with the basement and final touchup today......

We should be able to lock our interest rates starting tomorrow.....we will tentatively be home owners on July 31st....We are super excited to see the house come this far and we can't wait to get the keys to our house....

3 comments:

  1. Aspiring HVAC technicians in this state should not worry about getting the proper training that they need. HVAC Technician Salary in AL

    ReplyDelete
  2. It is one of the tedious task to maintain our garage efficiently. Only a good garage organization system can help you in this.

    ReplyDelete